//Water-infrastructure programme

Eastern Coast Flood-Protection Programme

Implementation of Flood Protection Measures in Various Areas of the Eastern and Northern Coast (Package 1 — Group 2)

Deep in the Hajar mountains of the UAE's eastern coast, National Contracting is building a generational line of defence against flash floods — three dams, protective dikes, a flood-conveyance channel and water infrastructure that together secure close to 2.8 million cubic metres of storm water.

Client Ministry of Energy and Infrastructure
Consultant Conser Consulting Engineering Services
Main contractor National Transport and Contracting Company
Duration 570 days
Start 22 April 2024
Completion 2 November 2026
0.0 million m³
Flood-water storage secured
0.0 metres
Height of the Shees RCC dam
0 metres
Protective dikes built
0 structures
Major structures, one programme

Commissioned by the Ministry of Energy and Infrastructure, this single programme unites nine major structures across three mountain-and-coast locations — Wadi Shees, Dhadna, and Qidfa & Murbah. Roller-compacted-concrete gravity dams, composite embankments, stone-lined channels and protective dikes are engineered to capture flash floods before they reach communities, store the water, and release it safely through controlled bottom outlets. It is among the most technically demanding civil works on the eastern coast — and a flagship of National Contracting's water-infrastructure capability.

RESERVOIR RCC GRAVITY DAM BOTTOM OUTLET 36.5 m
Anatomy of a gravity dam — capturing flood water, releasing it under control

Programme structures

Nine structures · three locations

Location 01 · Wadi Shees

Shees Dam

A 36.5-metre roller-compacted-concrete (RCC) gravity dam set deep in the mountains of Wadi Shees — engineered to arrest flash floods and bank 610,000 m³ of water behind a reinforced-concrete wall, released on demand through an HDPE bottom outlet with an electric valve.

Height
36.5 m
Crest length
104.5 m
Storage
610,000 m³
Type
RCC gravity dam

Location 02 · Dhadna

Dadna Dam

A 328-metre composite embankment dam pairing roller-compacted concrete with engineered fill (A1, A2, F1) and a rock-armour layer (R2) — the largest reservoir of the programme, impounding 1.187 million m³ of flood water behind a waterproofed core.

Length
328 m
Height
13 m
Storage
1,187,000 m³
Bottom outlet
HDPE + electric valve

Location 02 · Dhadna

Dadna Water Channel

A 1,594-metre flood-conveyance channel carrying released water safely through Dhadna — a 1,370 m trapezoidal stone-lined reach, a 178 m U-shaped reinforced-concrete section, and twin box culverts (3-cell and 4-cell) threading the flow beneath roads and crossings.

Total length
1,594 m
Stone-lined reach
1,370 m
U-channel (RC)
178 m
Box culverts
3-cell & 4-cell

Location 03 · Qidfa & Murbah

Murbah Dam & Protective Dikes

At Qidfa and Murbah the existing dam basin is expanded by 999,000 m³ and refurbished, flanked by two new protective dikes — a 1,628 m earthen dike (Dike-02) and a 1,510 m concrete dike (Dike-03) — together forming a 3.1-kilometre shield against coastal flooding.

Basin expansion
999,000 m³
Dike-02 (earthen)
1,628 m
Dike-03 (concrete)
1,510 m
Scope
Maintenance + new dikes

Companion water works

Potable-Water Pump Stations

Two new potable-water pumping stations — a main station and a booster station — built alongside the flood works to safeguard and distribute the community's drinking-water supply, delivered to the same standard of finish as the dams themselves.

Main station
Potable water
Booster station
Potable water
Build quality
Architectural finish

Access & connectivity

Dibba Bridge

A finished road bridge spanning the Dibba waterway — completed crossings, landscaped promenades and feature lighting that knit the coastal community together while the flood network quietly protects it.

Type
Road bridge over waterway
Works
Bridge, promenade, lighting
Status
Completed

Let's build what's next.

From the first survey to the final handover, National Contracting delivers infrastructure the nation relies on every day.

Get in touch