Client | Government of Sharjah |
Status | completed |
Category | Road and Bridge Projects |
Location | Sharjah |
Duration | 47 months |
➢ Construction of 3 grade separated interchanges comprising of bridge over Greenbelt Road at JN. 16B with a signalized junction at grade. A new grade separated clover leaf interchange at Junction 15B with Wasit Road at grade, with four loops to facilitate the turning movements and adjacent slip roads and services.
➢ Bridge construction over Third Industrial Road at junction 55A. Road comprises of approximately 4.30km of 3 lane dual carriageway with service roads on both sides.
➢ Majority of Services are laid at depths relative to existing ground levels.
➢ Works involve working in congested urban environment and involves major traffic management measures, relocation / protection of existing Services and laying of new major and minor services.